Integrated Scheduling Optimization of One-Way Channel Ships Entering and Leaving the Port, and Tugboat Distribution
Download PDF
$currentUrl="http://$_SERVER[HTTP_HOST]$_SERVER[REQUEST_URI]"

Keywords

Port management
One-way channel
Ship dispatching
Tug configuration

DOI

10.26689/jard.v6i6.4498

Submitted : 2022-10-31
Accepted : 2022-11-15
Published : 2022-11-30

Abstract

With the rapid development of shipping industry, the volume of maritime logistics is also increasing. Tugboats are the first service station for ships, and the working efficiency tugboats directly affects the ship’s attendance rate and the port’s service efficiency. Some domestic ports use one-way channel design due to the limitations of geographical position and natural factors. However, due to the particularity of the channel, the ships are entering and leaving the port in a disorderly manner and the tugboats are running empty, which causes problems in the port. Therefore, the port is in urgent need of improving the cooperative dispatching ability of one-way channel and tugboats.

References

Zheng H, Xu H, Liu B, et al., 2017, Collaborative Optimization of Ship Entering Sequence and Berth Allocation in Unidirectional Channel. Operations Research and Management, 26(09): 37–45.

Wu Y, Zhang R, 2022, Integrated Optimization of Continuous Berth Allocation and Ship Scheduling in Unidirectional Channel. Computer Engineering and Applications, 58(09): 246–255.

Yi J, Liu Z, Cai R, Huang X, et al., 2015, Simulation Decision of Port Tug Operation Configuration for Multi-berthing Base. Logistics Technology, 34(19): 105–109.

Yang Z, 2012, Port Tug Configuration Optimization Study. Journal of System Simulation Technology, 8(02): 169–174.

Bi X, Zhu H, Li B, 2017, Research on the Number of Auxiliary Tugs in Berthing Operation. Journal of Guangzhou Institute of Navigation, 25(03): 6–10.

Wang C, Wang X, 2019, Port Automatic Mooring System Under One-Way Channel Constraints. Port Science and Technology, 2019(12): 41–45.

Wang W, Zhao H, Li Q, 2013, Research on Optimization of Port Tug Scheduling for Multi-berthing Base. Computer Engineering and Applications, 49(13): 8–12 + 35.

Feng P, Deng C, Xu H, 2018, Simulation and Optimization of Port Tug Configuration in One-way Channel. China Water Transport (Second Half), 18(10): 68–70.

Zheng H, Liu B, Deng C, Feng P, 2018, Ship Scheduling Optimization of Bulk Cargo Port in Unidirectional Channel. Operations Research and Management, 27(12): 28–37.

Zheng H, Xu H, Cao H, 2017, Simulation and Optimization of Compound Channel Harbor Tug Configuration. Journal of Chongqing Jiaotong University (Natural Science Edition), 36(08): 102–109.